Challenge
Work is done without a notification, so history only shows part of it.
Agnotic approach
A simple request route that technicians use, and a rule for what must be recorded.

For maintenance and reliability leaders about to buy, build or roll out maintenance software. Agnotic Technologies reviews how work, plans, parts and data really flow at your sites, so the software is built on a process that works instead of copying the one that does not.
Trusted by global innovators
























Before you digitize
Yes, a maintenance process audit does exactly that: a fixed-scope review of how maintenance really runs before any of it is put into software. Agnotic Technologies follows work from the first notification to closure, then checks PM plans and task lists, asset criticality, spare parts, condition-based maintenance and root cause analysis practice, and the quality of the master data in your CMMS or SAP PM. Where you run several sites, we compare them side by side. You receive a findings report and a digitization roadmap that says what to fix in the process first and what to build. The audit is advisory and does not certify compliance with any regulation or standard.
The roadmap feeds straight into the next step, whether that is a new CMMS software build, a cleaner SAP PM setup or a multi-site maintenance standardization program. You own the report and can act on it with any team.
Audit checklist
The areas we review on every audit, what we check in each and the evidence we ask for. The scope call decides which areas matter most for your sites.
| Area | What we check | Evidence we look at |
|---|---|---|
| Work order flow | How a request becomes a notification, an order, scheduled work and a closed record, and where it waits | A sample of closed and open orders, status history, interviews with planners and technicians |
| PM plans and task lists | Whether plans match the assets that exist, intervals have a reason and tasks say what to check | Maintenance plans, task lists, PM completion records |
| Asset criticality | Whether a criticality rule exists, is applied the same way and drives priorities | Criticality ranking, asset hierarchy, priority codes on recent work |
| Spare parts | Which parts are linked to assets, how critical spares are chosen and how stockouts delay work | Bills of materials, stock records, orders waiting for parts |
| Condition-based maintenance | Which assets are monitored, who reads the data and how a reading turns into work | Route sheets, sensor or historian data, orders raised from readings |
| Root cause analysis | What triggers an RCA, which method is used and whether actions are closed | RCA records, action lists, repeat failures on the same assets |
| Master data quality | Functional locations, equipment records, failure codes and free text where codes should be | An extract from your CMMS or SAP PM, read by us, not changed |
| Site to site differences | Where sites name, code, plan and measure the same work differently | The same checks above, run at each site in scope |
We read data from extracts and change nothing in your live system. Findings name the process, not the person.
Because software copies the process it is given. If failure codes are free text, PM plans cover assets that were scrapped and nobody agrees what counts as downtime, a new CMMS records the same confusion faster and makes it harder to change.
An audit finds those gaps while they are still cheap to fix. It also tells you which problems software will solve and which ones need a decision, a rule or a conversation first.
You get a findings report and a digitization roadmap. The report lists each finding with its evidence, the site it applies to and how much it affects safety, cost or reliability.
The roadmap puts the work in order: process fixes first, then master data cleanup, then the software to build or configure. It is written so your own team or any vendor can act on it.
No. At sites covered by OSHA process safety management, the employer must certify its own compliance audit at least every three years, run by someone knowledgeable in the process. A maintenance process audit does not replace that audit and does not certify anything.
What it can do is make the mechanical integrity side easier to evidence: written procedures that match practice, inspection records that are complete and deficiencies that are tracked to closure. Your compliance team decides how to use the findings.
Access to the people and the data, for a short and agreed time. We interview planners, technicians, stores staff and reliability engineers, walk the site with a maintenance lead and read an extract from your CMMS or SAP PM.
Nobody has to prepare reports for us. We prefer the records as they are, because the gaps in them are part of the finding.
Failure points
What we find most often, and what the roadmap does about it.
Challenge
Work is done without a notification, so history only shows part of it.
Agnotic approach
A simple request route that technicians use, and a rule for what must be recorded.
Challenge
PM plans were copied from manuals and never reviewed against failures.
Agnotic approach
Plans for critical assets reviewed against their failure history before they are loaded into new software.
Challenge
Failure codes are optional, so most closures say 'fixed' in free text.
Agnotic approach
A short code list per asset class, made required at closure in the new system.
Challenge
Critical spares are not linked to the assets that need them.
Agnotic approach
Bills of materials for critical assets, so a planner sees the parts before scheduling the job.
Challenge
Condition readings are taken, but nobody turns them into work.
Agnotic approach
Clear limits and an owner for each reading, with orders raised when a limit is crossed.
Challenge
Each site uses its own words for the same asset, failure or priority.
Agnotic approach
A shared standard for names, codes and priorities, mapped from each site's local version.
Method
Six steps, agreed in writing before the audit starts.
We agree the sites, areas and systems in scope, who we talk to and what you want to decide after the audit.
You share an extract from your CMMS or SAP PM and the plans, task lists and RCA records in scope.
We follow real work at each site and talk to the people who request, plan, do and close it.
A sample of orders is traced from notification to closure, including the delays and the parts.
We go through the findings with your team before anything is final, so facts are checked and nothing is a surprise.
The findings report and digitization roadmap are handed over and walked through with your leadership.
The audit looks at the systems that hold maintenance work today, including the unofficial ones.
Notifications, orders, maintenance plans, task lists, catalogs and functional locations.
Work orders, PM schedules, asset records and failure codes in the system each site runs.
Spare parts, stock levels, reservations and purchase orders linked to maintenance work.
Route readings, vibration and other sensor data, and historian tags tied to assets.
Investigations, actions and repeat failures, wherever they are kept.
Shift logs, local trackers and paper checklists that hold work the system never sees.
Who it is for
Teams about to put money into maintenance software, or into fixing it.
Teams that want requirements based on how work really runs, not on a vendor demo.
Sites that want clean master data and agreed codes before the next go-live.
Operators that want to compare sites and agree one standard before building it.
Sites that want mechanical integrity records that are complete and easy to evidence.
Reliability teams checking that failure data is good enough to learn from first.
The audit is a fixed-scope engagement. If a site or area is added once it has started, we agree the change in writing before doing the extra work.
One site or several, with the areas, interviews and data agreed on the scoping call.
AuditA fixed-scope first release from the roadmap, such as a master data cleanup or one workflow, if you want us to build it.
BuildA team for the wider roadmap, working with your maintenance and IT staff, when the work is ongoing.
ScaleCost drivers
We do not publish prices. These are the drivers we size on the scoping call.
How many sites are in scope, and whether each one needs a visit.
Which of the audit areas matter most for the decision you need to make.
SAP PM, another CMMS, or a mix of systems and spreadsheets across sites.
How easily an extract can be taken, and how much history is useful.
How many roles and shifts we need to talk to at each site.
A priority list, or a roadmap detailed enough to start a build from.
Process safety management requirements for mechanical integrity and compliance audits, each linked to the regulation text on eCFR. They show what the employer's own records must support.
For process equipment covered by OSHA process safety management, 29 CFR 1910.119(j)(2) requires the employer to establish and implement written procedures to maintain the on-going integrity of that equipment.
Source: 29 CFR 1910.119(j)(2) (eCFR)29 CFR 1910.119(j)(5) requires deficiencies in covered equipment that are outside acceptable limits to be corrected before further use, or in a safe and timely manner when necessary means are taken to assure safe operation.
Source: 29 CFR 1910.119(j)(5) (eCFR)Under 29 CFR 1910.119(j)(6)(iii), the employer must assure that maintenance materials, spare parts and equipment are suitable for the process application for which they will be used.
Source: 29 CFR 1910.119(j)(6)(iii) (eCFR)29 CFR 1910.119(o)(1) requires employers to certify, at least every three years, that they have evaluated compliance with the process safety management standard to verify that its procedures and practices are adequate and are being followed.
Source: 29 CFR 1910.119(o)(1) (eCFR)29 CFR 1910.119(o)(3) and (o)(4) require a report of the compliance audit findings, a documented response to each finding and documentation that deficiencies have been corrected.
Source: 29 CFR 1910.119(o)(3) and (o)(4) (eCFR)References