    How Long Does Epic Integration Take? What Really Drives the Schedule

    By GauravNovember 26, 20269 mins read
    On this page

    Ask how long an Epic integration takes and you will hear very different answers, and most of them are true for someone. The engineering is rarely the slow part. The schedule is set by what kind of integration you need, how ready the health system is, how quickly security and contracts move, and how testing and go-live fit the hospital's calendar.

    This post does not give a number, because any single number would mislead. Instead it explains what drives the schedule, which steps sit on the critical path, what causes most delays and what vendors and health systems can do to shorten each step.

    How long does an Epic integration take?

    Planning an integration with an Epic customer?

    Our Epic integration page covers the FHIR, SMART on FHIR and interface work we build.

    How long an Epic integration takes depends less on coding than on five drivers: the type of integration, the health system's readiness and analyst capacity, the security review and contract, app setup and activation, and testing and go-live scheduling. Agnotic Technologies plans Epic projects around those drivers rather than a fixed estimate.

    A small read-only app and a two-way interface with write-back are different projects, even when both are called an Epic integration.

    Why is there no single answer?

    There is no single answer because much of the work happens inside the health system, on its schedule, with its people. A vendor controls its own build but not the customer's analysts, security team or change calendar.

    Two vendors building the same feature can see very different schedules at two hospitals, simply because one hospital has a sponsor and free analyst time and the other does not.

    Which integration types take the most effort?

    Effort grows with how much the integration changes inside Epic. Reading standard data through published APIs needs the least customer-side work, while writing data back or building custom interfaces needs the most.

    • Read-only FHIR app: standard APIs, scopes and app activation.
    • SMART on FHIR launch: adds launch setup inside the clinician's workflow.
    • Write-back: adds review of what is written, where it appears and who signs it.
    • HL7 v2 interfaces: adds interface build, network setup and message testing on the hospital's side.
    • Custom data or workflow: adds analyst build, design reviews and more testing.

    Standard APIs shorten the path

    Standard APIs shorten the path because the capability already exists in the customer's Epic system, so the work is setup and testing rather than new build.

    ONC certification criterion 170.315(g)(10) requires certified EHRs to offer a standardized API for patient and population services based on HL7 FHIR.

    The SMART App Launch implementation guide uses OAuth 2.0 and OpenID Connect so that apps can launch from an EHR with the user's and patient's context and only the access scopes they were granted.

    Design the first release around standard resources and scopes where you can, and leave anything that needs custom build for a later phase.

    Does Epic's own process add time?

    Yes, some. The vendor registers its app, gets credentials for each environment and the health system activates it in its own Epic instance. Each step has its own queue.

    Epic publishes its FHIR API documentation and developer resources for third-party applications on open.epic.com.

    Read the documentation for the APIs you plan to use before committing to a design, and confirm with the customer which ones its environment has enabled.

    How does the health system's readiness change the schedule?

    Readiness is usually the largest driver: a named sponsor, a clinical owner, Epic analysts with time assigned and a clear decision on where the integration fits in the workflow. Missing any of these stalls the project.

    • Sponsor: someone with authority to unblock security, contracts and analyst time.
    • Analyst capacity: Epic analysts assigned to the project, not fitted between other work.
    • Change calendar: upgrade freezes and other projects that block go-live windows.
    • Workflow decision: clinicians agree where the app or data appears.

    What should you ask before estimating?

    Ask the health system a short set of readiness questions before giving any schedule. The answers tell you more about the timeline than the feature list does.

    • Sponsor: who will approve priority and unblock decisions?
    • Analysts: which Epic analysts are assigned, and when is their time free?
    • Security: what does the review require, and how long is the current queue?
    • Environments: when can the vendor get non-production access and test patients?
    • Calendar: which upgrade freezes or other go-lives fall in the plan?

    Security review and contracts

    The security review and contract often run longer than the build. They involve questionnaires, evidence, architecture review, a business associate agreement and legal negotiation, each with its own reviewers.

    Start them at the first serious conversation, run them alongside technical work, and keep an evidence pack ready so each review starts from documents rather than questions.

    Testing environments and data

    Testing needs access to the customer's non-production environment, test patients that reflect real workflows and testers from the clinical side. Waiting for any of these holds the project.

    Ask for environment access and test patients as soon as the contract allows, write test scripts with clinical users early, and agree who signs off each workflow before testing starts.

    Work that can run in parallel

    Much of the work can overlap if it is planned that way. The vendor can build against public sandboxes while the security review and contract move, and clinical workflow design can run alongside the build.

    Some steps cannot overlap. Activation in the customer's environment usually waits for security approval, production access waits for the contract, and go-live waits for testing sign-off. Put those gates on the plan so everyone can see what each one is waiting for.

    What causes most delays?

    Delays mostly come from dependencies nobody owned. These patterns recur.

    • Late security review: started after the build is finished.
    • No analyst time: the customer's Epic team assigned but not available.
    • Scope creep: write-back or custom data added after the plan was agreed.
    • Missed windows: go-live blocked by an upgrade freeze nobody checked.
    • Unclear workflow: clinicians disagree on where the integration appears.

    How can you shorten an Epic integration?

    Shorten it by starting the slow, non-technical steps first, keeping the first release on standard APIs and agreeing ownership on both sides.

    • Parallel tracks: security, contract and environment requests started alongside the build.
    • Narrow first release: standard read access first, write-back later.
    • Named owners: one person per dependency on each side.
    • Calendar check: go-live windows and freezes confirmed at kickoff.

    A worked example: the same app at two hospitals

    A vendor's SMART on FHIR app reading medications and problems went live quickly at one hospital. The hospital had a sponsor, its Epic analysts had time assigned and the security review began during contracting.

    At a second hospital, the same app waited for a security reviewer, then for analyst time, then for a change window after an upgrade. The code was identical; the schedule was set by readiness. Nothing the vendor did in engineering would have changed it, but earlier questions about reviewers, analysts and freezes would have set honest expectations.

    For later customers, the vendor asked readiness questions in its first meeting and planned each project around the answers.

    Who owns the critical path?

    Every dependency on the critical path needs an owner, on whichever side controls it.

    • Vendor: app build, documentation, evidence pack and test support.
    • Health system sponsor: priority, analyst time and decisions.
    • Health system security and legal: review and contract.
    • Epic analysts: activation, build and environment access.
    • Clinical owners: workflow decisions and test sign-off.

    How should you plan and track the schedule?

    Plan with milestones and owners rather than a single end date, and track the dependencies that sit outside your team every week.

    • Milestones: contract signed, security approved, app activated, testing passed, go-live.
    • Dependencies: each with an owner, a status and a date requested.
    • Risks: freezes, staff changes and scope changes logged as they appear.
    • Lessons: what slowed each customer, fed into the next project's kickoff.

    What are best practices for planning an Epic integration?

    Ask readiness questions before quoting a schedule, start security and contracts early, keep the first release on standard APIs and scopes, and confirm go-live windows at kickoff.

    Name an owner for every dependency on both sides, track them weekly, and record what slowed each project so the next one starts better prepared.

    How Agnotic can help

    Agnotic helps vendors and health systems plan and deliver Epic integrations: choosing the path, scoping a first release on standard APIs, preparing security documents, building and testing the integration, and coordinating with Epic analysts through go-live.

    Plan your Epic integration with Agnotic

    Our Epic FHIR capabilities page covers what Epic's APIs offer and how we build on them.

    Sources

    Frequently Asked Questions

    It depends on the integration type, the health system's readiness, security review and contracts, app activation and testing windows, more than on coding.